How a major Canadian tailings dam improves monitoring data and increases personnel safety, while cutting costs

Country Canada
Sector Mining
Project Type Tailings dam monitoring
Main Product Monitoring Solution

Challenge

GKM Consultants, a Worldsensing Partner based in North America, was tasked with installing a monitoring system at a tailings dam attached to a major iron ore mining operation in northern Quebec, Canada. It was a challenging assignment: the mine is a large producer of iron concentrate and the area covered by the tailings dam stretches over several square kilometers.

Any monitoring solution would not only have to operate reliably over massive distances but also keep working at temperatures well below zero for much of the year.

Solution

At the start of the project, tens of manually surveyed piezometers that had been installed in previous years had to be automated. A key concern for GKM Consultants was to reliably automate instruments in locations where a failure could compromise mining operations. These critical instruments were connected to Vibrating Wire data loggers to enable (near) real-time monitoring-. In more recent developments, Measurand SAAs were automated with a Digital Logger to support new developments of the mining complex.

GKM Consultants, an established geotechnical and structural instrumentation firm independently tested and selected Worldsensing’s industrial monitoring products as the most appropriate to read the instruments automatically and relay the data back to a central base station, where the data is integrated into a database. Worldsensing’s technology was the best fit for the project because of its optimal combination between a 900 Mhz long-range radio communication (LoRa) with a signal a sensitivity of 120 dBm, lithium battery with low power consumption and flexibility to integrate any type of vibrating wire instruments across a large area.

The technology was able to cover all the critical areas of the tailings dam, including regions with natural barriers. This location made real-time communication challenging, but GKM was able to overcome the problem by increasing the data logger sampling rate to make sure that at least one reading per hour would get through.

Benefits

The main benefit of the Worldsensing monitoring solution is a reduction in costs compared to manual data collection. The mine operator now has access to data from across all the critical areas of the tailings dam without having to send technicians out into the field to take data logger readings. The real-time data provided by the data loggers means the mine operator can monitor dam conditions continuously, making sure there is no risk to mining operations or personnel. 

And the high quality of the  Worldsensing devices means they are able to withstand the harsh Canadian winter, operating without fault for many years even though ambient temperatures can drop to -40ºC. Combined with a power consumption that can extend battery life up to a decade, this means technicians rarely need to venture into the field to tend the monitoring equipment, further reducing costs and risks.

About GKM Consultants

GKM Consultants bridges instrumentation technologies and complex monitoring assignment into a single turnkey servicing company for the benefit of their clients. GKM Consultants is a leader in monitoring services and data acquisition devices, which range from simple data-logging machines to sophisticated systems that relay the acquired data to a central server. GKM Consultants provides a range of geotechnical services that include instrument installation, data hosting and monitoring that offer functionalities such as alarm handling and management, and remote data visualization.

How a major Canadian tailings dam improves monitoring data and increases personnel safety, while cutting costs

Are you planning a project?

Get in touch with us to share your needs and project requirements. We are experts in engineering and IoT and are happy to help.